From Ritu Raj | Product & Market Analysis
AEP Data Center Load: 84 GW Signed, 35 GW Take-or-Pay, Built Figure Undisclosed
On this page
American Electric Power says 84 GW of new load is contracted through 2031, more than twice the 37 GW peak its whole system carried. Only 35 GW of that sits under take-or-pay contracts. Another 46 GW is Texas letters of agreement. AEP data center load is now the core of a $100 billion capital plan, and the company does not publish how much of it is running.
Key takeaways
- AEP's 84 GW headline mixes three different commitments. On the Q3 2026 earnings call, management split it into 35 GW under take-or-pay electric service agreements and 46 GW under Texas letters of agreement. Another 3 GW in PJM and SPP is not yet converted to take-or-pay.
- Minimum-take terms are real where the tariffs apply. AEP's Q3 2026 10-Q describes take-or-pay minimums covering 80% to 90% of contracted demand and contract periods of up to 20 years. AEP Ohio's tariff makes early exit cost about what staying would.
- AEP publishes no figure for contracted load already running. Our calculation from its sales tables puts added average commercial load at about 1.5 GW over the past year, against 84 GW signed.
- The $100 billion plan rests on the firm tier, not on Texas. Management says PJM and SPP contracted load is largely in the plan, while about 85% of the $17 billion Texas budget is allocated to reliability work.
The short answer. AEP has signed far more data center load than it has built, and it does not say how much is running. Of 84 GW contracted through 2031, 35 GW carries take-or-pay terms that would hold if AI demand stalled. The 46 GW in Texas rests on letters of agreement backed by about $2 billion of security.
What AEP's 84 GW of data center load actually counts
AEP reported on 28 October 2026 that incremental contracted load had reached 84 GW through 2031. The release says a project counts only if it is backed by "fully executed electric service agreements or letters of agreement". Those two documents do not bind a customer to the same thing.
An electric service agreement, or ESA, is the contract under which a utility serves a customer on tariff terms. A letter of agreement, or LOA, is an earlier commitment that reserves a place in line. AEP's release treats them as one category. Its earnings call does not.
The 84 GW is also not all data centers. AEP last gave a share in February 2026, when data centers including crypto made up 88% of the pipeline. Assume the mix is similar and you are close, but no current figure exists.
| Tier | GW | Share | Backing | Region |
|---|---|---|---|---|
| Firm contracts | 35 | 42% | Take-or-pay electric service agreements | PJM and SPP |
| Not yet converted | 3 | 4% | Signed, not take-or-pay. AEP expects near-term conversion | PJM and SPP |
| Texas letters | 46 | 55% | SB 6 compliant letters of agreement | ERCOT |
| Total | 84 | 100% |
Gigawatt figures are management's, from the Q3 2026 earnings call. Shares are our arithmetic and sum to 101% through rounding. Several press summaries of the slide deck swap the 35 GW and 46 GW labels. The transcript settles it.
The number has also changed horizon
The tally was 24 GW in August 2025, 28 GW in October 2025, 56 GW in February 2026, 63 GW in May and 69 GW in July. The move to 84 GW also moved the end date from 2030 to 2031, so the latest step is not like for like.
Most of the most recent jump is one site. CFO Trevor Mihalik attributed about 9 GW of the 15 GW added in the quarter to the Piketon project in Ohio. One campus accounts for 60% of the quarter's growth.
Minimum-take terms in AEP's large load tariffs, state by state
The contract question that matters is whether a customer keeps paying after it stops needing the power. In the tariffs AEP has won, the answer is mostly yes. AEP's Q3 2026 10-Q describes approved and proposed provisions with contract periods of up to 20 years and take-or-pay minimums covering 80% to 90% of contracted demand. The same provisions carry credit support and make customers responsible for specified infrastructure.
The terms that bite are set state by state, and two of them are public enough to test.
Ohio: an exit that costs about what staying costs
AEP Ohio's data center tariff took effect on 23 July 2025. It sets the minimum monthly demand on a sliding schedule that cannot exceed 85% of total contract capacity, up from 65% under the prior tariff. For a site of 1 GW, the cap binds and the minimum billing demand is 850 MW.
The term equals the load ramp, capped at four years, plus eight years. An exit opens only after the fifth year following the ramp, and costs 36 months of minimum charges. Add those together and you get five years of service plus three years of fees, the same eight years the contract already required. I read that as a cancellation right with no discount.
Credit is the other half. Customers without ratings of at least A- from S&P and A3 from Moody's, and without qualifying cash, must post collateral equal to 50% of total minimum charges for the full term. Surety bonds are not accepted.
Indiana: an 80% floor with a 20% give-back
Indiana Michigan Power's settlement, approved on 19 February 2025, applies to new or expanded sites of at least 70 MW. Initial contracts run at least 12 years, and can start after a ramp of up to five years. The settlement filing sets minimum billing demand at the greater of 80% of contract capacity or 80% of the highest established demand.
Customers can reduce contract capacity by up to 20% without a fee after the first five years, on 42 months' notice. Take both terms at full use. A 1 GW customer can drop to 800 MW and owe a minimum on 80% of that, a floor of 640 MW or 64% of the original contract. Our arithmetic, and it is the softer of the two states.
| Term | AEP Ohio | Indiana Michigan Power | AEP Texas letters of agreement |
|---|---|---|---|
| Minimum demand | Up to 85% of contract capacity | 80% of contract capacity or peak | None disclosed |
| Contract term | Ramp of up to 4 years, plus 8 | At least 12 years, plus ramp of up to 5 | None disclosed |
| Early exit | After year 5 post-ramp, 36 months of minimums | Exit fee. Up to 20% reduction without one after 5 years | Staged security refund or forfeiture |
| Credit support | 50% of total minimums, unless rated A-/A3 | Not confirmed in sources we opened | About $50,000 per MW, per our calculation |
| Where A wins | Tightest exit of the three | Longest fixed term | Fastest way for AEP to fill a queue |
Ohio and Indiana from the tariff page and regulatory filings. Texas security is $2 billion divided by 40 GW of prospective load, from AEP Texas's Q2 2026 10-Q, and is our calculation. Other AEP jurisdictions have their own terms, not compared here.
The 46 GW of AEP Texas load is a different kind of commitment
More than half of the 84 GW is in Texas, where AEP is a wires company. Its own Q1 2026 release said the timing of Texas load is highly dependent on generation, which is supplied by others. AEP does not control when that power exists.
Mihalik said the entire 46 GW is backed by fully executed SB 6 compliant letters of agreement. SB 6 is the Texas law behind the state's large load rules. On the money behind them, CEO Bill Fehrman was specific: "We have collected over $2 billion of cash or collateral just for Texas".
AEP Texas's Q2 10-Q ties about $2 billion of security to 40 GW of prospective load in ERCOT's Batch Zero. That works out to $50,000 per MW. The figure matches the security level Texas regulators later wrote into the rule.
What a walk-away would cost in Texas
The Public Utility Commission of Texas adopted its large load rule, 16 TAC 25.194, on 18 September 2026. According to a Steptoe and Johnson summary, an intermediate agreement requires $50,000 per MW in refundable security. A customer that withdraws after capacity is allocated, but before the deadline for a full interconnection agreement, forfeits 20% of it.
That is $10,000 per MW, or $10 million per GW. If the customer neither withdraws nor signs by the deadline, it loses all of the security, or $50 million per GW. Those are small sums against the cost of a campus of that size.
AEP has not said that its letters match this structure, and it has not said what they require beyond SB 6 compliance. Nothing in the release, the call or the coverage we opened describes a minimum take in the letters. I would not count them as take-or-pay until AEP says so in a filing. Once a customer signs the fuller interconnection agreement, the rule ties refunds to minimum billing demand milestones, so the firmness improves later in the process.
ERCOT's classification adds a further discount. Of 45 GW AEP submitted to Batch Zero, 16 GW was categorised as base load and 29 GW as study load. Fehrman said ERCOT will file its data center audit report on 10 December. Compare how this reads against the way contracted capacity is treated in neocloud valuations.
Signed against built: the AEP load figure that is missing
Neither the Q3 release nor the call states how much contracted load is energized. The closest dated disclosure we found is from October 2025, when about 2 GW of data centers came online in the third quarter of 2025. That is one quarter, a year old, and not a running total.
The sales tables are the next best evidence. Between Q3 2025 and Q3 2026, commercial retail sales rose to 8,475 GWh from 7,355 GWh in the vertically integrated utilities. They rose to 14,885 GWh from 12,610 GWh in the transmission and distribution utilities. That is 3,395 GWh of added sales.
Divide by the 2,208 hours in the quarter and you get about 1.5 GW of added average commercial load. The nine-month numbers give the same answer, about 1.6 GW. I treat that as the best available public proxy for what has actually shown up in a year, and it is a rough one.
Put the contracted figure on top of the 37 GW peak and you get 121 GW, 3.3 times the current system. That matches Fehrman's statement that demand should more than triple by 2031. The earlier target, published in October 2025, was 65 GW by 2030.
How the $100 billion AEP capital plan maps onto contracted load
AEP's plan for 2027 through 2031 puts about $37 billion into transmission, $36 billion into generation and $22 billion into distribution. It takes the rate base from about $87 billion in 2026 to $162 billion in 2031. Spending on this scale elsewhere in the AI build has drawn more attention, but the same question applies: which dollars depend on demand that has not arrived?
The plan's exposure is narrower than the headline implies. Mihalik said contracted load signed in PJM and SPP is "largely reflected in the capital plan". Of those 38 GW, 35 GW is take-or-pay, which is 92%. The firmest tier and the capital are in the same place.
Texas sits mostly outside the bet
The Texas capital plan is $17 billion, and management said about 85% of that is allocated to system reliability and resiliency work. The remaining 15% is about $2.6 billion. The broader Texas load build and the 765 kV expansion are excluded from the plan.
So the largest and softest block of contracted load carries the least capital today. It also means the 46 GW is an option on future plan increases rather than the reason for the current one. That is the opposite of how the 84 GW headline reads.
Piketon goes a step further. Utility Dive reports that SoftBank and its affiliates will pay for the transmission serving the SB Energy campus, a project of roughly $5 billion. That is up from the $4.2 billion AEP Ohio cited in March. Three 765 kV lines of about 3.2 GW each are targeted for year-end 2028, 2029 and 2030. Management calls it a 20-year agreement backed by an investment grade counterparty. A customer funding its own wires is the cleanest protection in this whole structure.
The balance sheet is the place where a miss would show. AEP says FFO to debt sits within its 14% to 15% target, above a 13% downgrade threshold. It also says it added $22 billion of capital with $5.2 billion of new equity. That is the same discipline question covered in the credit analysis of Oracle's backlog and the review of high-yield data center bonds.
If AI data center demand stalls, which AEP contracts hold
A stall would not hit the tiers evenly. The table is my reading of the disclosed terms, and it assumes demand falls enough for customers to stop building.
| Tier | GW | What the customer still owes | My verdict |
|---|---|---|---|
| Take-or-pay ESAs, PJM and SPP | 35 | Minimums of 80% to 90% of contracted demand for up to 20 years, with credit support | Holds, subject to who the payer is |
| Not yet converted, PJM and SPP | 3 | Unclear until the contracts are signed | Most likely to shrink, but small |
| ERCOT letters | 46 | Forfeited security on the published rule, $10,000 to $50,000 per MW | Does not hold as revenue, and little capital is at stake yet |
| Piketon transmission | About 9 | A 20-year agreement that funds the lines | Holds if the counterparty does |
Piketon is shown separately for emphasis. It is part of the PJM total, not an addition to it. The verdicts are the author's judgement and are not AEP statements.
A stall would hurt AEP's growth story far more than its contracts. The company has guided to 9% to 11% annual earnings growth, and rate base growth above 13%. If Texas load does not arrive, future plan increases do not happen and the stock's reasoning changes. Existing customers, by contrast, are protected by design. AEP says the contracts could offset up to $21 billion in fixed costs for residential customers over their lives.
Minimum-take also differs from revenue on the whole bill. In Ohio and Texas, AEP is a wires company, so the protection covers delivery charges, not the price of the energy. Anyone modelling a stall should start with the demand charge alone.
The closest analogy on this site is the hyperscaler lease commitments that have not yet commenced, which are also binding but not yet running. Customer concentration at CoreWeave shows what the same dependency looks like when the counterparty is thinner.
Where this argument is weakest
Three things could make this piece look too harsh or too comfortable.
A small built figure is what a back-loaded ramp looks like
Comparing 1.5 GW of arriving load with 84 GW signed is striking and partly unfair. These contracts run through 2031, and the Ohio tariff lets contract capacity ramp over four years. A gap this large in 2026 is exactly what you would expect if every signature were sound. My proxy also includes weather, as the 8.9% rise in residential sales in the vertically integrated utilities suggests, and non-data-center customers.
Take-or-pay is only as good as the payer
AEP has not given a current split between hyperscalers and developers. In October 2025, about 80% of the 28 GW then signed came from hyperscalers, according to Utility Dive. A minimum from a special purpose developer with a thin balance sheet, and the 50% collateral requirement in Ohio only partly closes that gap. The 92% firmness ratio above tells you about contract form, and says nothing about credit.
The evidence base has limits too. I could not open AEP's full 10-Qs, the Indiana settlement or the Texas rule directly. Those terms come from search excerpts of the filings and a law firm summary. If AEP's letters of agreement contain minimum bills that nobody has published, the Texas tier is firmer than I have scored it. Fehrman told analysts the signed load in ERCOT is real, and $2 billion of security is not nothing.
What to read in AEP's next filings
Three disclosures would settle most of this, and two are datable.
| Watch | When | What would change my view |
|---|---|---|
| ERCOT data center audit report | Expected 10 December 2026 | A sharp cut to the 16 GW base load group |
| Conversion of the 3 GW in PJM and SPP | Next earnings update | Conversion slipping for a second quarter |
| An energized figure in GW | Any AEP filing | AEP publishes one at all, which would turn this from inference into measurement |
If you follow how a capex slowdown would feed through to software multiples, the ERCOT report is the near-term date to mark.
Frequently asked questions
How much data center load has AEP contracted?
AEP reports 84 GW of incremental contracted load through 2031, as of its third quarter 2026 results on 28 October 2026. That total covers all large customers, and data centers made up 88% of the pipeline when AEP last gave a share in February 2026. About 35 GW is under take-or-pay electric service agreements, 46 GW is under Texas letters of agreement, and 3 GW in PJM and SPP has not yet converted.
Do AEP data center contracts have minimum take requirements?
Yes, in the utility tariffs. AEP's third quarter 2026 10-Q describes approved and proposed provisions with contract periods of up to 20 years and take-or-pay minimums covering 80% to 90% of contracted demand, plus credit support. AEP Ohio's tariff caps the minimum at 85% of contract capacity. AEP has not said its Texas letters of agreement carry a minimum take.
How much of AEP's contracted load is already built?
AEP does not publish that figure. Neither its third quarter 2026 release nor its earnings call states how much contracted load is energized. The last dated disclosure we found is about 2 GW of data centers coming online in the third quarter of 2025. Commercial sales growth implies roughly 1.5 GW of added average commercial load over the past year, which is a rough proxy and includes non-data-center customers.
What happens to AEP if data center demand slows?
The firm tier keeps paying. About 35 GW carries take-or-pay terms, and AEP says its PJM and SPP contracted load is what sits largely in the $100 billion plan. The Texas tier is different: AEP holds over $2 billion of security against it, and most of its $17 billion Texas capital is allocated to reliability work. A slowdown would hit growth targets well before it reached existing customers' bills.
What is an SB 6 letter of agreement?
AEP uses the phrase for its 46 GW of Texas load but has not published the form. SB 6 is the Texas law behind the state's large load interconnection rule, adopted on 18 September 2026 as 16 TAC 25.194. A law firm summary of that rule describes $50,000 per MW of refundable security at the intermediate agreement stage. A commitment of that kind is a reservation with money behind it, which is weaker than take-or-pay.
Is AEP's $100 billion capital plan dependent on AI data centers?
Partly. The plan puts about $37 billion into transmission, $36 billion into generation and $22 billion into distribution from 2027 through 2031. Management says the PJM and SPP contracted load is largely reflected, while the broader Texas build is mostly excluded. Reliability and existing system needs also drive a meaningful share, so the answer is not simply yes. No filing we opened gives a single data center share of the plan.
How to read a utility's contracted load this week
Take the next utility headline you see on data center gigawatts and split it the way this post splits AEP's. Write three columns: take-or-pay, reserved with security, and everything else. If the company will not give you the columns, the transcript usually will.
Then look for one sentence that says how much is energized. If you cannot find it, you have found the same gap that sits under the 84 GW.
Related on this site
Backlog and signed commitments are the common thread. Compare AEP's split with how the cloud providers report remaining performance obligations.
References
- AEP, Q3 2026 earnings release, Form 8-K Exhibit 99.1, 28 October 2026. Used for 84 GW, capital plan, rate base, residential offsets and sales tables.
- Motley Fool, AEP Q3 2026 earnings call transcript, 28 October 2026. Used for the 35, 3 and 46 GW split, Texas capital, collateral and credit metrics. Machine-assisted, with garbled words noted in the text.
- AEP, Form 10-Q for Q3 2026, and AEP Texas, Form 10-Q for Q2 2026. Used for minimum-take range and Batch Zero security. Read as search excerpts.
- AEP Ohio, Data Center Tariff, retrieved 9 November 2026, and Vorys, client alert on the PUCO order, 11 July 2025.
- Utility Dive, Indiana Michigan Power settlement, 25 November 2024, and IURC approval, 20 February 2025. The 80% minimum comes from an excerpt of Cause No. 46097 filings.
- Steptoe and Johnson, What 16 TAC 25.194 means for your next project, 19 October 2026. Secondary summary of the adopted rule.
- Utility Dive, AEP Q3 2026 investment plan, 29 October 2026, and MGRID, AEP capital plan coverage, 29 October 2026. Used for Piketon.
- AEP, Q1 2026 release, 5 May 2026; Utility Dive, 1 August 2025 and 30 October 2025; T&D World, 12 February 2026. Used for the load history and 2 GW figure.
The weakest part of this source base is that the terms of AEP's Texas letters of agreement are not public, and the 10-Qs and Indiana filing were read as excerpts rather than whole documents. Every figure was last verified on 9 November 2026. Refresh after the ERCOT audit report due on 10 December 2026 and AEP's next quarterly filing.